Update on the Coronach Community Hall

As many are aware, there was a fire in the Community Hall on November 3, 2021. Town Council has been navigating through the insurance process and the first step will be to complete an asbestos abatement. Three quotes were received and Council has hired Firmin Abatement Specialists to complete the work for $52,000. The abatement is planned to begin as soon as the contractors schedule allows.

Once this is complete there will be a thorough building structural inspection to ensure restoration is possible. Town Councils intention is to restore the building if it can be completed within the insurance coverage of $741,000 for the building and contents.

The timeline for the abatement will be 2 weeks once work begins. The public will be updated again once structural information is received.